From Yun Xi Beh who tested the Oracle content:
Align
Plan - Would be good if there can be more detailed steps tied to the local territory around project compliance
Define - listed activities generally applicable
Strategy and op model activities scope generally different from the activities that will be included in Oracle implementation. E.g. Portfolio analysis, pricing analysis, go-to-market strategy
Innovate
Release development
Generally we will do Level 4 process flow for Oracle ERP (with reference to P1 activities)
Would prefer more detailed selection of the modules, as there are many modules not in use, e.g. Workforce health, Journeys, etc
UAT kickoff not included under UAT activities currently
Perform defect remediation seems to be repeated, there a standalone task, as well as in the UAT / SIT tasks
Data migration rehearsals for P2, SIT, UAT is missing
Release
Production configuration and setup, and prod data migration seems to be missing here?